Jeff mock's pdev spectrometer
03jun08
pdev
hardware: description, specs, and measurements.
Monitor
pdev hardware (fans, temps, voltages)
pnetctl:
controlling pdev from cima
Maintenance
procedures
Diagnostics
Datataking measurements
pdev
software: jeff mock's and ao additions
File descriptions:
pdev
users guide (.pdf)
idl routines to process the .pdev and .fits files
Psrfits
test data.
Galfacts info.
Notes:
areca raid controller (1220)
manual (.pdf)
History:
- See also:
- 110919
- replaced
b5sxg0 box 104 with box 112. Chris had problems with jumps in b5s1g0
- The
jumps in the spectra looked like bit flips in the data.
- when
running adjpower, there were many a/d overflows (looking at
/tmp/pdevsig.log on pdevs1). If the bit flips were occurring, they must
have been occuring vary early in the pipeline since the a/d overflow
bit check is right after the a/d and mux switch. This bit then gets
carried along with the data sample. Since the bit and the data
sample were probably bad, it really must have been a problem at the
early stages.
- Ran
diagnostics before box 104 replaced.
- ltest,rtest ok
- rdcomp failed. mainly with b5s1g0.
(b1s1g1 also failed a lot).
- 1106xx:
- 11jun11:
pdevs6 disc? in raid fails. replaced
- 17jun11:
pdevs2 disc2 in raid fails. replaced
- 100908
- pdev-113,
pdevs7, b6sxg0 fan2 (gxb) dropouts). looks like power supply trouble
- pdev-113
replaced with pdev-109
- 100902:
- pdev-107,
pdevs3,b2sxg0 fan 2 replaced.
- 090906:
- b1sxg0 boxes fan failed, fpga died. This
was pdev-109. Replaced with pdev-103.
- 090214:
- Swapped
I,Q cable in spectrometer box: b6s1g1 (bm 6, high band, polA): dig
i0,q0 signal cables swapped inside spectrometer box. Probably occurred
when the dig levels were changed from 1.5 to .78 volts. Group1
has not yet been used for datataking. 090216 check all the other boxes
for i/q switches.. None other found.
- 081205: replaced disc 5 on pdevs1 raid.
- The
disc i/o had not been keeping up with galfacts datataking
(occasionally).
- The
raid stats showed that disc 5 had more seek errors, timeout cnts..
- 081010
- Accidentally overwrote pnetctl.html.. Grabbed backup from
12sep08.. and then fill in some of the lost stuff.
- B2SxG1 switched out spectrometer box pdev-105 . replaced with
pdev-122. connects to pdevS10 server. digitizer S0 IA was giving
problems.
- 081001:
- Used a test program to write as fast as possible to a psrfits
file (input came from memory) (.ps) (.pdf).
- 080821: svn checkout https://mock.com/svn/pdev/web web on
pdevs1:/home.local/pdev/pdev to get the web files for the
website.
- 080615: timedomain
sampling.
- Does not have an
8 bytes hdr rec. psrv.c was treating those bytes as a rec header
and byteswapping them.
- psrv.c was also using the fftlen to compute how
many blks fit in 1 second. Updated so it used the sample rate.
- pnetbld now correctly computes how long each block takes in
time domain mode.
- 080614: polA,polB
or stokesI is stored as unsigned int while fits uses signed.
Changed bpOut.c to clip to maximum signed value for these pols.
- 080613: ashift
computation in pnetbld. Shift up by 1 more for
stokesU,V relative to pola,polB. This makes the rms of U,V the
same as polA,B since jeff outputs 2*polA,2*polb, but only 1*U, 1*V. (Note: 13jun08 i shifted 1 less for
u,v..17jun08 i corrected it to shift 1 more). check data
- 080608: pnetbld changed default
hr_shift to be 12-alog2(sqrt(dec)). see fpga dlpf and parameters
hr_shift. check
- 080415:attenuation before a/d
changed by 6db.. went from 1.5 to .78 v to get 2048 counts.
NOTES:
These notes need to eventually be added to the
documentation above:
- 0910220: pnet 1 second messages output to the user
- 36.49 MB/s 20.68 MB [1:1]/1000 blocks (0.1%)
- Iorate:
- This is a cumulative (in time) i/o rate from the start of the
observation.
- Computed in the prun spectrometer (prun_rmtdma()). Output by
pnet.
- The i/o rates from all of the spectrometers are summed.
debug mode probably lets you see individual rates.